Challenges of Land reclamation at Royal Pier Waterfront (RPW), Southampton
Forming new property from
the sea has gotten sophisticated, even as the relentless tides are a force to
be reckoned with. But it’s worth the investment.
The new scheme at Royal Pier in Southampton will be constructed partly on existing land at
Mayflower Park and Town Quay, and partly on land reclaimed from the sea. It is
this reclaimed land that presents the major challenge for Lucent Group
("Lucent") on this project.
As participants in a joint venture land opportunity know, any work undertaken on the coastline is always going to
be difficult, but the scale of the reclamation at Royal Pier Waterfront
("RPW") presents its own trials. In essence Lucent will build a dam
out into the Test Estuary using sheet piling that stretches from the existing
Red Funnel ferry terminal right out to the tip of the old pier structure, then
returning back in a straight line to the western end of Mayflower Park. This
will create a 13 acre lagoon, and the next step will be to pump out most of the
sea water which will leave a large ‘hole’ – ideal to be made into a large
basement and exactly what Lucent plans to do.
There are a number of issues in doing this, not least
of which is installing the sheet piling in the first place. This requires long
‘W’ section steel sheets to be driven into the sea bed from a floating barge,
and these sections must interlock through a system of clutches to create a
reasonably water tight seal with its neighbour. Once the sheet piling is
complete the water can be pumped out.
The next challenge is keeping the water out so that
work can commence on the basement structures. This is done by using
‘dewatering’ plant, which consists of sinking a number of tubes into the seabed
around the perimeter to create a system of wells from which the remaining water
can be pumped away. This lowers the water table and creates a dry working area.
Because there is a lot of porous gravel under the seabed, water pressure from
the tide causes the ground water level to fluctuate throughout the day, placing
a varying demand on the dewatering plant during the course of 24 hours.
Once the ground water is under control, a level
platform needs to be created on the seabed. This level platform is called
a piling mat. This consists usually of a thick layer of crushed rubble and
provides a stable working area so that plant and machines can begin
constructing the basement.
The sheet piling installed earlier now needs to be
stabilised to prevent it from being damaged by the action of the waves. One of
the traditional ways to do this would be to sink ‘sacrificial’ piles into the
seabed and connect these to the sheet piles using steel tie rods. However
because we are creating a basement, we can use the concrete floor slab to
stabilise the piles instead, while a reinforced waterproof concrete wall is
constructed behind the sheet piles. Investors in joint venture partnerships want to know they are building on a solid
foundation, literally and figuratively. By this
point we should have 13 acres of reclaimed land on which to commence
construction.
Comments